The short answer
A stage gate process divides product development into stages of work separated by gates. At each gate, senior managers who control the money review agreed deliverables against agreed criteria and decide: go, kill, hold or recycle. Robert G. Cooper created the Stage-Gate model; the name first appeared in print in 1988. Hardware teams use it because each next step, such as tooling, a certification slot or a production order, commits real money.
What are the stages?
In Robert G. Cooper’s Stage-Gate® model, discovery feeds five stages, each opened by a gate:
| Stage | What happens |
|---|---|
| Discovery and ideation | Opportunities are found and ideas generated |
| 1. Concept | A quick first assessment of the idea |
| 2. Build the business case | A detailed investigation that ends in a business case |
| 3. Development | Detailed design and prototypes of the product and how it will be made |
| 4. Testing and validation | Proof that the product works, the market accepts it and operations can deliver |
| 5. Launch | Full production, ramp-up and rollout |
Each company adapts the stages. The principle stays: the further you go, the more each stage costs, so you decide on purpose before entering it.
What is a gate?
A gate is a decision meeting before the next stage, run by the senior managers who own the resources. In Cooper’s model it has three parts:
- Deliverables: what the team brings from the stage just finished, such as test results, an updated plan and costs.
- Criteria: what the project is judged against, covering both readiness and value, agreed before the stage starts.
- Outputs: a clear decision (go, kill, hold or recycle) and an agreed plan. For a go, that means the budget, people, timeline and deliverables for the next stage, and the date of the next gate.
A gate that never says kill or hold is a status meeting. The decision is the point.
How do the stages map to hardware builds?
This is how we map it in our work with hardware teams; companies differ.
| Cooper’s stage | Typical hardware work | Gate before the next spend |
|---|---|---|
| Concept, business case | Requirements, architecture, looks-like and works-like prototypes | Commit to the design and the first build |
| Development | EVT: does the production-intent design work? | Commit to tooling and certification |
| Testing and validation | DVT and PVT: does it meet all requirements, and can the factory build it? | Commit to production |
| Launch | Mass production and ramp | — |
The build stages are explained in EVT, DVT and PVT in Jira.
Is a stage gate process compatible with agile?
Yes. The gates decide when to commit money; they don’t dictate how the team works between them. Cooper’s own later generations of Stage-Gate build in frequent build-and-test cycles and sprints inside a stage. Firmware and software can run in sprints, and each sprint adds evidence for the next gate. Modified Agile for Hardware Development is one framework built for this mix.
How do you run a stage gate process in Jira?
This is our setup, not an Atlassian template.
- One milestone per gate, as a release (version) with a target date, on the same timeline as the sprints. The space timeline shows the space’s releases next to the work.
- Gate criteria written before the stage starts, as a checklist or linked work items on the milestone.
- Work linked to the gate it is needed for: firmware features, board revisions, test cases and long-lead parts. A late item then shows which gate is at risk.
- A dashboard per gate with the criteria, the open work, the test results and the parts still missing, so the review is a decision and not a status hunt.
- The decision recorded on the milestone: go, go with conditions, hold, recycle or kill, with reasons and owners for what stays open.
One limit to plan around: a space timeline shows work from one space only. Across several spaces you need a plan, which Atlassian includes in Jira Premium and Enterprise, or an app. We build Gatecast for Jira for this.
Where do teams usually go wrong?
- Criteria are written in the week of the gate, so they fit whatever is ready.
- The gate is decided from slides that were out of date when they were made.
- Hardware, firmware and mechanical plan in different tools, so nobody sees which late item moves the gate.
- Every gate ends in “go”, and the real decision happens later, when the money is already spent.
Start with your next gate, not the whole program: write its criteria, link the work that must be ready, and run one gate this way.
Sources
- Robert G. Cooper, The Stage-Gate® model: an overview, Stage-Gate International, checked 24 November 2026.
- Robert G. Cooper, “The New Product Process: A Decision Guide for Managers”, Journal of Marketing Management, 1988.
- Atlassian, What does the space timeline show?, checked 24 November 2026.
The Hardware Stage-Gate Readiness Check: 18 questions, about six minutes, your score right away.
Questions people ask
Who invented the stage gate process?
Dr. Robert G. Cooper. He coined the term Stage-Gate, which first appeared in print in 1988, and the model has been in use since the late 1980s. Stage-Gate® is a registered trademark, so many companies run their own variant under generic names such as phase gate or tollgate.
Is a stage gate process the same as waterfall?
No. Waterfall describes how the work inside a project is sequenced. A stage gate process describes when the business decides to keep investing. Teams can work in sprints inside a stage and still hold a gate before the next commitment of money; Cooper's own later versions of the model build in-stage sprints in.
How many stages does a stage gate process have?
Cooper's model has discovery plus five stages: concept, build the business case, development, testing and validation, and launch, with a gate before each stage. Companies adapt the number to the product; hardware teams often tie the later gates to their builds, EVT, DVT and PVT.